“If it works, why change it?” We hear that on every site. In November 2026 we changed it anyway. On the first day of a five-storey steel frame at Saxley Court in Horley, the setting-out was not marked with a tape and a chalk line. A robot printed it onto the concrete.
The robot is called HP SitePrint. This article explains what it is, how robotic setting-out works, what it printed on our slab, the figures HP publishes for it and where its limits are. We are a steel frame contractor and we do not sell the machine, so this is a user’s account.

At a glance
- HP SitePrint is a three-wheeled robot that prints a site layout directly onto the floor slab.
- It works from a 2D CAD file (.dxf) and is positioned by a robotic total station tracking a prism on the robot.
- It prints lines, arcs, points and text, so gridlines and panel references can be labelled on the floor.
- HP quotes up to ten times the productivity of manual layout, with one operator.
- HP’s published layout accuracy is up to ±3/32 in, about 2.4 mm, in its high accuracy mode.
- It needs line of sight to the total station and does not print in rain or through puddles.
What is HP SitePrint?
HP SitePrint is a construction layout robot. HP’s own description is the simplest one: a robotic printer on wheels that prints the layout of a construction site directly onto the slab. It is small enough to carry, runs on batteries and drives itself around the floor while it prints.
It is not a new idea in the UK. The first trials here were reported in 2023, when John Sisk & Son tested the robot for printing layouts and gridlines. What has changed since then is that the machine has moved from trials on large contractors’ sites to everyday use, including by specialist trades like ours.
How robotic setting-out works
The robot does not know where it is on its own. It works as a pair with a robotic total station, the same surveying instrument a setting-out engineer already uses. The process has three stages, as HP describes it.
1. Prepare the drawing
The layout is exported as a 2D CAD file in .dxf format, which can be generated from the BIM model. The file carries three things: the elements to print, the known obstacles on the floor such as columns and stair openings, and the control points.
2. Set up on site
The total station is set up against the control points on the slab and locked onto the tracking prism on top of the robot. From then on the total station measures the angle and distance to the prism continuously, and that is how the robot knows its position. The operator loads the drawing and chooses what to print from a tablet, phone or laptop. The robot creates its own Wi-Fi hotspot, so the site does not need a network.
3. Print
The robot drives the layout and prints as it goes. Its progress shows live on a map of the drawing. Sensors stop it at edges and at obstacles that were not on the drawing. HP supplies two batteries, each good for up to four hours of continuous layout, which covers a working day.
What the robot printed on our slab
Saxley Court is a full-build, pre-panelised frame, so the slab needed the position of every wall panel. This is what was on the concrete at the end of the first day:
- Wall lines. Continuous lines along each wall, giving the position of the base track.
- Openings. Rectangles marking where each opening falls within the wall.
- Gridlines. Crossed lines with the label printed beside them in plain text: “GRIDLINE 5”, “GRIDLINE B”.
- Panel references. The reference of each panel, printed on the floor where that panel stands.
The text is the part a chalk line cannot do. A manual set-out gives you lines. The robot gives you lines with their meaning written next to them. When a panel comes off the lorry with a reference on it and the same reference is printed on the slab, nobody has to stop and open a drawing.
The slab was ordinary site concrete, rough in places and with trowel marks. The lines printed cleanly across it. HP says the floor needs no more preparation than it would for a manual layout, and that matched what we saw.




Robot or tape and chalk line?
| Manual setting-out | Robotic setting-out | |
|---|---|---|
| Where dimensions come from | Read from a drawing and transferred by hand | Taken directly from the CAD file |
| Crew | Typically two or three people | One operator, according to HP |
| What ends up on the floor | Lines and hand-written marks | Lines, arcs, points and printed text |
| Labels | Written by hand, if at all | Gridlines and references printed in place |
| Main source of error | Misreading or mis-measuring a dimension | Inaccurate control points or an out-of-date drawing |
| Weather | Works in most conditions | Not in rain or standing water |
The last two rows matter. A robot does not remove the possibility of error. It moves it. If the control points are wrong or the drawing is the wrong revision, the robot will print the mistake perfectly.
What the numbers say
We have used the robot on one project so far, so we are not going to quote a figure of our own yet. These are the ones HP publishes:
- Productivity: up to ten times that of the manual process, with one operator. HP notes that the result depends on the density and complexity of the layout.
- Accuracy: layout accuracy of up to ±3/32 in, about 2.4 mm, in high accuracy print mode with HP’s spherical prism and a one-second total station (HP specification).
- Winvic: a full site layout completed three times faster, with a 45% cost reduction.
- ACCIONA: 1,951 metres of drywall track marked across a ten-floor hospital, six times faster than the conventional process.
The two project examples are from HP’s published case studies. They are a manufacturer’s figures and should be read that way. What we can say from our own first day is narrower and, for us, more useful: the layout was on the slab, it was complete, and the installers started from it.
Why it matters for pre-panelised steel frame
Robotic layout is usually talked about for drylining and M&E. We think it fits panellised steel frame even better, for three reasons.
Panels cannot be adjusted on site. A factory-made, pre-boarded panel arrives at a fixed size with its openings formed. The slab has to match the factory, because the factory is not going to match the slab. Our full-build panellised system page explains why that accuracy is the whole point of the method.
Errors travel upwards. In a loadbearing frame the studs have to line up floor over floor. A wall that starts a few millimetres out on the ground floor is still out five storeys later, and by then it is carrying load. The checks behind that are covered on our structural engineering page.
The base track is permanent. It is fixed into the concrete at close centres. Lifting and re-fixing it is slow and leaves holes in the slab. The cheapest time to get a wall in the right place is before the first fixing goes in.
What it does not do
- It does not replace the surveyor. Control points still have to be established and checked. HP is direct about this: the layout is as accurate as the control points.
- It needs line of sight. The total station has to see the prism. Columns, stored materials and other trades on the slab all get in the way.
- It does not like water. HP says it can print on a damp surface, but not through puddles or in rain. On an open slab in a British winter, that is a planning constraint.
- It needs a clear floor. The more clutter on the slab, the less the robot can print in one pass.
- It depends on the drawing. The file has to be prepared properly and it has to be the current revision.
Our view after the first day
Construction is slow to change, and some of that caution is earned. A method that has worked for decades should not be dropped for a gadget. But skilled people are hard to find and expensive to waste, and asking them to spend a day measuring lines onto concrete is not the best use of them.
Technology will never replace the value of good people, but the right technology will allow good people to achieve so much more.
Having seen it work, we would find it difficult to go back to setting out a panellised frame by hand. If you are planning a steel frame project and want to know how we would set it out and install it, our SFS installation page is the place to start, and this page explains how we work with main contractors.
Frequently asked questions
What is HP SitePrint?
HP SitePrint is a construction layout robot made by HP. It is a small three-wheeled printer that drives across a floor slab and prints the setting-out directly onto the surface, working from a 2D CAD drawing and positioned by a robotic total station.
How accurate is HP SitePrint?
HP publishes a layout accuracy of up to plus or minus 3/32 of an inch, which is about 2.4 mm, when the robot is used in its high accuracy print mode with HP’s spherical prism and a one-second total station. In practice the layout can only be as accurate as the control points the total station is set up from.
Does a layout robot replace the setting-out engineer?
No. Someone still has to establish accurate control points, set up the total station, prepare the drawing and check the result. The robot replaces the repetitive part of the job, which is transferring hundreds of dimensions from a drawing to the floor by hand.
Can HP SitePrint work on rough concrete and outdoors?
Yes, within limits. HP lists rough and polished concrete, tarmac, plywood and formwork among the surfaces it prints on, and says it can work on a damp surface. It cannot print through standing water or in rain, and it needs a clear line of sight to the total station.
How long do the printed lines last?
It depends on the ink. HP supplies inks that fade in days, weeks or months, so the layout can be matched to how long the lines need to stay visible before they are built over.
How much faster is robotic setting-out than doing it by hand?
HP says up to ten times the productivity of manual layout, with one operator in place of a crew of two or three. Its published case studies range from three times faster to six times faster on real projects. The result depends on how dense and complex the layout is.